And a delightful time was had by all

Comments Off on And a delightful time was had by all

…who weren’t there.

/PHOTO_20180215_113532

Yeah, it’s been a day of plumbing – so all the runs under the house are complete. Ish. Insofar as they go from the place where they’re meant to start, through the floor, along under the floor and then they pop out in what will, at some point, be our furnace cupboard.

It’s sort of a hybrid of a manifold and a series run system. Each bathroom has 2 feeds of hot and cold – the shower (and in the main bathroom the shower/bath), and also the toilet* & sink**. The kitchen only gets one run (which feeds the refrigerator, dishwasher, pot filler and the main kitchen sink. It’ll also feed the outside hose for the back garden). The laundry gets its own run too – from which I intend to vamp the front-garden-hose tap.

That should mean that, for the most part, the hot and cold water demands don’t lead to massive fluctuations in temperature anywhere where we care. Although I refuse to get non-temperature controlled showers anyway. Having lived with them as a student and as a kid such barbarism is unacceptable in a house we build. I squeal for no-one in the shower***.

So the next step in our JIT purchasing is that I’m ordering a nice adequate manifold, and shall install it in such a way as we can just unscrew it and pop the drywall behind it. Then I need to finish the rough-in and get it checked. Much of it is done to the point of the nipple on which the taps will go. There are however a few bits that still need doing, and I need to get the laundry and fridge boxes bought and installed.

….

I do feel sorry for anyone who wandered past our house today and heard the crawlspace shouting “You complete bastard, why do you keep coiling that way!”. It turns out that while PEX is way easier than copper in many regards, its persistent desire to be a coil wrapped around you, under-floor posts, itself, other bits of pex, any random bit of anything it can find… is quite irritating when you’re working at 3< °>C / 37< °>F. Mind, I was warm enough under there because I was scrabbling around and trying to hold my head and neck out of the ratshit.

And yes, there are fresh, err, deposits, down there.

I was very glad for my filter mask.

Anyhow, I said mostly done because I ran out of clips, and all that pipework needs insulating. Oh, and (of course), there’s still the soil (DWV) pipe to run. I pulled out a section of the old today, and am starting to ponder the new. But most of that needs the top-plates installed on our walls and we’ve only installed one layer of top plate (because then we can use the second layer to help tie things together).

I’m hoping to hell that we’re doing this right. I will be really, really f’kin sad if we’ve got any of this wrong, but the inspector looked at our work and said “just keep doing what you’re doing”. So we are.

* Yes, hot *and* cold to the toilet because I think a bidet is potentially a good idea. But only if it has warm water.
** Which I still refuse to call a lavatory, despite what I wrote on the plans for the building, because that’s just wrong.
*** Uh, I’ll just leave that there.

KateWE

Kate's a human mostly built out of spite and overcoming transphobia-racism-and-other-bullshit. Although increasingly right-wing bigots would say otherwise. So she's either a human or a lizard in disguise sent to destroy all of humanity. Either way, it's all good.